Subject: Riverside Commercial Center Electrical Subcontract – Requested Revisions
Hi [Contractor Contact],
Thank you for sending over the subcontract for the Riverside Commercial Center electrical scope. We reviewed it from our project-performance and payment-risk standpoint, and there are several provisions we need to revise so the agreement aligns with the price and risk assumptions in our proposal.
The main items for us are:
1. Payment: Sections 3.2 and 3.3 make Owner payment an express condition precedent and shift Owner nonpayment/insolvency risk to us. We can accept a reasonable pay-when-paid timing mechanism, but not a clause that makes us finance the Owner's credit risk indefinitely.
2. Retainage: The 10% retainage held until final completion and final payment on the entire project is too long for a trade package of this size. We need retainage reduced and released based on completion of our work, not unrelated closeout by others.
3. Changes and claims: We need compensation for directed changes performed before paperwork catches up, and the 2-business-day claim deadline needs to be extended to a workable notice period.
4. Delay and schedule: The current language allows schedule changes at any time, imposes uncapped liquidated damages of $1,000/day, and waives all delay-related costs even for Contractor- or Owner-caused impacts. We need time and cost relief for resequencing, acceleration, disruption, and delays not caused by us.
5. Indemnity and insurance: The indemnity should be limited to the extent of our negligence and aligned with applicable law and available insurance. We also need the insurance requirements tied to actual policy forms and commercially available endorsements.
6. Bonds and lien rights: If 100% performance and payment bonds are required, the premium needs to be added to the subcontract price. We also cannot provide unconditional lien waivers for unpaid amounts or waive mechanic's lien rights in advance.
7. Termination: If there is a termination for convenience right, payment needs to include work performed, stored materials, demobilization, and reasonable overhead and profit.
8. Cure rights and dispute process: We need notice and an opportunity to cure before default termination, and dispute venue should be the project county rather than Contractor's home county.
If helpful, we can turn comments quickly and send back a marked-up draft with targeted revisions on these points. Once those items are addressed, we should be in a much better position to move forward.
Thanks,
[Contractor/Subcontractor Name]
Punchlist AI Analysis