👀 You are viewing a SAMPLE REPORT.Analyze your own document

Sample Construction Subcontract Analysis

A subcontract that shifts major payment and schedule risk downstream: an explicit pay-if-paid clause, a Contractor disclaimer of any duty to pay amounts the Owner does not pay (for any reason), an unconditional lien waiver through the application date that includes unpaid amounts and retainage, and broad one-sided indemnity.

Reviewed by the BizLeaseCheck Editorial Team · Last updated May 26, 2026 · Informational analysis, not legal advice.

Critical risk indicatorsConstruction contract

This is the same report shape every BizLeaseCheck analysis produces: a 0–100 danger score, prioritized red flags with verbatim evidence quotes, the key dates buried in the document, and a tailored negotiation email draft.

8 red flags
4 key dates
Evidence-backed
Email draft included
Want the deep explainer behind a construction contract? Read the construction contract guide cluster.
See construction contract guides
Executive Summary
Document: Construction contractReviewed for: the Contractor

This subcontract is highly unfavorable to the Subcontractor and shifts major payment, schedule, delay, indemnity, lien, and termination risk downstream. The most severe issues are: an explicit pay-if-paid clause making Owner nonpayment and insolvency the Subcontractor's risk; 10% retainage held until final completion and final payment on the entire project; unconditional lien waivers covering unpaid amounts and retainage; a 2-business-day claims deadline; uncapped liquidated damages of $1,000/day; a broad no-damages-for-delay clause; broad-form indemnity including Contractor/Owner negligence; mandatory 100% performance and payment bonds at Subcontractor's expense; and termination for convenience that excludes overhead, profit, and demobilization. The subcontract also incorporates the prime contract whether or not the Subcontractor reviewed it, and pushes differing/concealed site-condition risk onto the Subcontractor at no additional cost. Several of these clauses may be limited by state-specific law depending on the project location, especially contingent payment, anti-indemnity, lien-waiver, mechanic's lien, and no-damages-for-delay provisions. From the Subcontractor perspective, this agreement should be revised before signing.

96Danger score
Construction Terms Overview- Subcontract

Contract price / basis

Lump sum $480,000

Pay-if-paid / pay-when-paid?

Yes

Liquidated damages

$1,000 per day, uncapped

Governing law

Law of the state where the project is located

Payment terms

Monthly payment applications; payment is expressly contingent on Contractor's receipt of payment from Owner; Contractor may withhold for actual or alleged deficiency in its sole discretion

Retainage

10% retainage; released only after final completion, Owner final acceptance of entire project, and Contractor receipt of final payment

Change orders

Written change order signed by Contractor required before changed work; verbal instructions/field directives/sketches not compensable; claims due within 2 business days

Schedule & delay

Time is of the essence; Contractor may change schedule at any time; no-damages-for-delay; Subcontractor must continue work during disputes

Liquidated damages

$1,000 per day, uncapped

Scope & exclusions

Electrical scope; broad prime-contract flow-down; Subcontractor assumes obligations whether or not it reviewed prime documents; differing/concealed/unforeseen site conditions at no additional cost

Indemnification

Broad-form indemnity including claims caused in whole or in part by Contractor or Owner negligence; additional insured primary/non-contributory; waiver of subrogation

Insurance & bonds

Additional insured requirement; waiver of subrogation; Subcontractor must furnish 100% performance and payment bonds at its own expense; no bond protection furnished for Subcontractor

Lien rights & waivers

Unconditional waiver and release of lien and bond rights through application date including unpaid amounts and retainage; waiver of mechanic's lien rights to fullest extent permitted by law

Termination

Immediate termination for cause without cure; termination for convenience at any time with payment limited to documented direct cost of work performed and no overhead, profit, demobilization, or lost profit

Dispute resolution

Binding arbitration in Contractor's home county; continued performance required during dispute; prevailing-party attorneys' fees

Critical Dates & Deadlines

Don't miss these dates. Add them to your calendar immediately.

Monthly Payment Applications

Date not specified|Subcontractor must submit monthly payment applications.

Change/Claim Notice Deadline

|Any claim for additional time or money must be submitted in writing within two business days or it is waived.

Completion Per Contractor Schedule

Estimate
Date not specified|Subcontractor must complete strictly per Contractor's schedule, which may be changed at any time.

Retainage Release

Estimate
Date not specified|Retainage released only after final completion, Owner's final acceptance of the entire project, and Contractor's receipt of final payment from Owner.

Detected Red Flags

Download Redlines (DOCX) View Source PDF
CriticalIssue Score: 100/100
Express pay-if-paid clause shifts Owner nonpayment and insolvency risk to Subcontractor

Why it's dangerous

This is explicit contingent-payment language. If the Owner delays payment, disputes payment, or becomes insolvent, the Contractor can argue it never has to pay you. On a $480,000 lump-sum subcontract, this can put the full contract value at risk. Enforceability varies sharply by state, so project-state counsel should assess whether this clause is enforceable where the project is located.

Negotiation Tactic

Frame this as a bankability and pricing issue: you cannot finance the Owner's credit risk and would need to increase price materially if asked to do so.

Suggested Redline

Contractor shall pay Subcontractor for undisputed amounts within seven (7) days after Contractor's receipt of payment from Owner attributable to Subcontractor's Work, but in no event later than thirty (30) days after Subcontractor's proper payment application. Owner nonpayment or insolvency shall not be a condition precedent to Contractor's payment obligation except to the extent caused solely by Subcontractor's material breach.
CriticalIssue Score: 99/100
Contractor disclaims any duty to pay if Owner does not pay for any reason

Why it's dangerous

This goes beyond timing and attempts to eliminate payment entirely whenever Owner does not pay, even if the reason is unrelated to your work, such as Owner insolvency, lender issues, disputes with Contractor, or upstream paperwork problems. That creates near-total collection risk for earned work.

Negotiation Tactic

Point out that you cannot accept being the insurer of Owner credit and Contractor administration failures; if left unchanged, the subcontract price should be revised upward to reflect financing risk.

Suggested Redline

Contractor may withhold from Subcontractor only amounts actually withheld by Owner solely and directly due to Subcontractor's defective or incomplete Work, and only to the extent reasonably necessary to protect Contractor. Contractor remains responsible for payment of all other earned amounts.
CriticalIssue Score: 99/100
Unconditional lien waiver covers unpaid amounts and retainage

Why it's dangerous

This is one of the most dangerous clauses in the subcontract. It requires you to waive lien and bond rights for work not yet paid and for retainage as a condition to progress payment. If payment is delayed, dishonored, or disputed, you may have already waived your security rights. Lien-waiver enforceability is state-specific and should be reviewed under the project state's statute.

Negotiation Tactic

This is a standard accounting-control fix: waivers should match money actually received, not future or retained amounts.

Suggested Redline

As a condition to payment, Subcontractor shall provide a conditional waiver and release only to the extent of the amount actually requested for payment. Upon receipt of cleared funds, Subcontractor shall provide an unconditional waiver limited solely to the amount actually received, expressly excluding retainage, pending change orders, disputed amounts, and work not yet paid.
CriticalIssue Score: 97/100
No-damages-for-delay clause bars compensation even for Contractor- or Owner-caused delay

Why it's dangerous

This forces you to absorb labor inefficiency, extended general conditions, overtime, remobilization, and acceleration costs even when delay or interference is caused by Contractor or Owner. On a labor-heavy electrical scope, these costs can be substantial. Enforceability of no-damages-for-delay clauses varies by state and exceptions may apply, so project-state counsel should review.

Negotiation Tactic

Emphasize that schedule flexibility is acceptable, but not uncompensated disruption caused by others.

Suggested Redline

Subcontractor shall be entitled to an equitable adjustment in Subcontract Time and Subcontract Price for delays, disruption, acceleration, interference, resequencing, or extended performance caused by Contractor, Owner, design professionals, separate contractors, or events beyond Subcontractor's reasonable control. Any no-damages-for-delay limitation shall not apply to active interference, bad faith, gross negligence, or delays exceeding thirty (30) days.
CriticalIssue Score: 96/100
Broad-form indemnity includes claims caused by Contractor or Owner negligence

Why it's dangerous

This is broad-form indemnity that attempts to make you defend and indemnify Contractor and Owner even for their own negligence. Many states restrict or void this by anti-indemnity statute, but enforceability is state-specific. Even if narrowed by law, the clause invites tender and defense-cost disputes and may exceed available insurance.

Negotiation Tactic

Present this as a statutory-compliance cleanup and insurance-alignment issue rather than a refusal to stand behind your work.

Suggested Redline

To the fullest extent permitted by applicable law, Subcontractor shall indemnify and hold harmless Contractor and Owner, but only to the extent of bodily injury or property damage caused by the negligent acts or omissions of Subcontractor or those for whom Subcontractor is legally responsible. Subcontractor shall have no obligation to indemnify or defend any indemnitee for that indemnitee's own negligence, willful misconduct, or breach of contract.
CriticalIssue Score: 95/100
10% retainage held until entire project final completion, final acceptance, and final payment

Why it's dangerous

You are financing 10% of your contract price—about $48,000—potentially for many months after your electrical work is complete. Release is tied to the entire project and Owner final payment, so delays by other trades or Owner closeout can hold your money long after your scope is done.

Negotiation Tactic

Quantify the financing burden: $48,000 held for months materially affects labor and material cash flow and will be priced into the job.

Suggested Redline

Retainage shall not exceed five percent (5%). Retainage on Subcontractor's Work shall be reduced to two percent (2%) upon fifty percent (50%) completion of Subcontractor's Work if performance is satisfactory, and all retainage shall be released within thirty (30) days after Subcontractor's final completion of its Work and delivery of required closeout documents, regardless of completion of unrelated work by others.
CriticalIssue Score: 95/100
Broad waiver of mechanic's lien rights

Why it's dangerous

This attempts to strip one of your main payment remedies. Combined with pay-if-paid and unconditional waivers, it leaves you with very little security if payment problems arise. Whether pre-work lien waivers are enforceable depends heavily on state law.

Negotiation Tactic

Explain that lien rights are a last-resort payment remedy and should not be waived in advance, especially where no upstream payment bond protects you.

Suggested Redline

Nothing in this Subcontract shall constitute an advance waiver of Subcontractor's mechanic's lien, bond, stop-notice, or other statutory payment remedies. Any waiver shall be effective only to the extent of payments actually received and only as permitted by applicable law.
CriticalIssue Score: 94/100
Two-business-day deadline waives all claims for extra time or money

Why it's dangerous

A 2-business-day notice period is extremely short for documenting impacts, pricing changes, and tracing causation, especially on active jobsites. Missing the deadline could waive otherwise valid claims for change-order, delay, acceleration, or disruption costs.

Negotiation Tactic

Explain that your field team can give prompt heads-up, but pricing and impact analysis often require more than 48 hours.

Suggested Redline

Subcontractor shall provide written notice of claims for additional time or compensation within seven (7) days after Subcontractor first becomes aware of the event giving rise to the claim, and shall provide supporting documentation within a reasonable time thereafter. No claim shall be waived absent material prejudice to Contractor.

Negotiation Email Draft

Subject: Riverside Commercial Center Electrical Subcontract – Requested Revisions Hi [Contractor Contact], Thank you for sending over the subcontract for the Riverside Commercial Center electrical scope. We reviewed it from our project-performance and payment-risk standpoint, and there are several provisions we need to revise so the agreement aligns with the price and risk assumptions in our proposal. The main items for us are: 1. Payment: Sections 3.2 and 3.3 make Owner payment an express condition precedent and shift Owner nonpayment/insolvency risk to us. We can accept a reasonable pay-when-paid timing mechanism, but not a clause that makes us finance the Owner's credit risk indefinitely. 2. Retainage: The 10% retainage held until final completion and final payment on the entire project is too long for a trade package of this size. We need retainage reduced and released based on completion of our work, not unrelated closeout by others. 3. Changes and claims: We need compensation for directed changes performed before paperwork catches up, and the 2-business-day claim deadline needs to be extended to a workable notice period. 4. Delay and schedule: The current language allows schedule changes at any time, imposes uncapped liquidated damages of $1,000/day, and waives all delay-related costs even for Contractor- or Owner-caused impacts. We need time and cost relief for resequencing, acceleration, disruption, and delays not caused by us. 5. Indemnity and insurance: The indemnity should be limited to the extent of our negligence and aligned with applicable law and available insurance. We also need the insurance requirements tied to actual policy forms and commercially available endorsements. 6. Bonds and lien rights: If 100% performance and payment bonds are required, the premium needs to be added to the subcontract price. We also cannot provide unconditional lien waivers for unpaid amounts or waive mechanic's lien rights in advance. 7. Termination: If there is a termination for convenience right, payment needs to include work performed, stored materials, demobilization, and reasonable overhead and profit. 8. Cure rights and dispute process: We need notice and an opportunity to cure before default termination, and dispute venue should be the project county rather than Contractor's home county. If helpful, we can turn comments quickly and send back a marked-up draft with targeted revisions on these points. Once those items are addressed, we should be in a much better position to move forward. Thanks, [Contractor/Subcontractor Name] Punchlist AI Analysis

More sample reports

Every BizLeaseCheck document type produces a report like this. Browse other examples:

Commercial leaseCommercial LeaseA retail triple-net (NNN) lease with an uncapped operating-expense pass-through, a landlord relocation right, and an unlimited personal guaranty.View sample Residential leaseResidential LeaseAn apartment lease with a three-month security deposit, compounding late fees, an auto-renewal trap, a waiver of the warranty of habitability, and a self-help lockout clause.View sample Personal guarantyPersonal GuarantyA continuing, unlimited personal guaranty with joint-and-several liability, a waiver of defenses, and no burn-off — the clauses that put the signer’s personal assets on the line.View sample Business funding / MCABusiness Funding / MCAA merchant cash advance with a high factor rate (and the estimated true APR it hides), a confession of judgment, fixed daily ACH debits, and a hard-to-use reconciliation provision.View sample SBA loanSBA Loan PackageAn SBA 7(a) loan with an uncapped unconditional personal guaranty, joint-and-several liability for every 20%+ owner, available home-equity collateral, and lender authority to pursue guarantors before liquidating business collateral.View sample Franchise FDDFranchise Disclosure (FDD)A franchise disclosure document with a heavy fee stack (royalty + brand fund + tech + supplier rebates), broad no-cure termination triggers, a Gross Sales definition that includes amounts you may never collect from delivery platforms, and reserved encroachment rights (online, delivery, kiosk, wholesale) inside your market.View sample Vendor / SaaS MSAMSA / SaaS ContractA vendor-favorable SaaS MSA where the Customer carries multiple effectively uncapped liability buckets while the Vendor caps its own exposure at 12 months of fees, with a broad Customer indemnity, no termination for convenience, and acceleration of all remaining fees on early termination.View sample CRE purchaseCRE Purchase AgreementA commercial real-estate purchase agreement where $125,000 of earnest money goes hard immediately on deposit, the inspection period is only 10 days, the sale is broadly AS-IS with a disclaimer of all reps, and Buyer is asked to release Seller from all environmental, latent-defect, and unknown claims.View sample Business purchaseBusiness / Asset PurchaseAn asset purchase agreement that quietly assumes nearly all pre-closing liabilities (including unknown ones) to the Buyer, makes the contractual indemnity the sole and exclusive remedy in a way that purports to bar fraud claims, and provides no escrow, holdback, or indemnity security from the Seller.View sample Equipment financeEquipment Finance AgreementA non-cancelable equipment finance agreement structured economically like a financed purchase but drafted with lease-style remedies: explicit hell-or-high-water payment even if equipment never works, acceleration of all remaining payments plus residual on default, and evergreen 12-month auto-renewals at full payment if notice is missed.View sample Employment / NDAExecutive Employment AgreementAn executive employment agreement with a 24-month nationwide non-compete covering any connection with any competing business, a confidentiality clause that purports to bar disclosure to government agencies, and an IP-assignment provision that captures personal-time inventions with no carve-out.View sample LLC / operating agreementLLC Operating AgreementAn LLC operating agreement that concentrates control in the Manager — mandatory capital calls with only 10 business days to fund, 2x dilution plus voting suspension plus a 15% priority loan as the default penalty, and a departure valuation that uses book value with stacked 25% minority and 25% marketability discounts.View sample Commercial insuranceCommercial Insurance PolicyA Business Owner's Policy issued to a software consulting and data-hosting business where the core professional and technology services appear excluded, a separate endorsement removes professional and tech claims, flood is excluded even though the location is in a FEMA Special Flood Hazard Area, and the cyber sublimit is only $25,000.View sample Assumed leaseAssumed Lease (DD)A commercial retail lease being assigned to an incoming restaurant tenant: under 12 months remaining on the term, no transferable renewal option, an existing monetary default that the assignee would inherit, uncapped NNN/CAM exposure, and a landlord recapture right that can terminate the lease instead of consenting to the assignment.View sample